E.J. Thomas Parking Deck

Repair and restore 110,550 gsf concrete deck on all levels. Repair or replace all expansion joints. Install new waterproof membrane from entrance to first turn after Ticket Office.


Details

  • Construction Start Date: January 2000
  • Construction Complete Date: November 2000
  • Professional Design Services: Karl R. Rohrer Associates, Inc., Akron, Ohio
  • Construction Management: Ozanne Construction, Inc., Cleveland, Ohio
  • Total Budget: $ 438,448 (local funds)