Polsky Parking Deck Phase IV (West Campus)

Repair and restore Broadway Street exit ramp. Repair and restore 316,190 gsf deteriorated concrete on first, second, and third floors. Repair and restore all expansion joints. Paint all structural steel. Install new waterproofing membrane.


Details

  • Construction Start Date: May 2000
  • Construction Complete Date: December 2000
  • Professional Design Services: Desman & Associates, Cleveland, Ohio
  • Construction Management: The Hammond/Bennett Joint Venture Canton, Ohio
  • Total Budget: $ 3,256,027 (local funds)