Exchange Street Parking Deck

Repair and restore 370,303 gsf deteriorated concrete on levels 1 to 5 and drive ramps. Repair/install expansion joints. Install new waterproof membrane. Clean and paint all structural steel. Repair existing standpipe system. Install exterior panels.


Details

  • Construction Start Date: May 2000
  • Construction Complete Date: April 2001
  • Professional Design Services: Braun & Steidl Architects, Inc., Akron, Ohio
  • Construction Management: Ozanne Construction, Inc., Cleveland, Ohio
  • Total Budget: $ 2,770,091 (local funds)