Polsky Parking Deck Phase V
Renovation of 128,900 gsf in Polsky Parking deck level two, including replacing the concrete deck, painting structural steel and installing a traffic coating.
Details
- Construction Start Date: August 2001
- Construction Complete Date: December 2001
- Professional Design Services: Desman Associates, Cleveland, Ohio
- Construction Management: Hammond/Bennett, Joint Venture, Canton, Ohio
- Total Budget: $ 2,429,665 (local funds)