Leigh Hall Rehabilitation
This project involved the total rehabilitation of the existing 58,254 gsf building as a Distance Education Center.
Details
- Construction Start Date: August 2002
- Construction Complete Date: August 2003
- Professional Design Services: TC Architects, Inc., Akron, Ohio
- Construction Management: The Hammond/Bennett Joint Venture, Canton, Ohio
- Total Budget: $ 6,934,129 (state and local funds)