SAS Phase II (Central Stores)

Renovate 18,500 gsf in the west half of the lower level of the Student and Administrative Services Building for the relocation of Central Stores, Mailing Services, and Printing Services.


Details

  • Construction Start Date: July 2002
  • Construction Complete Date: October 2002
  • Professional Design Services: Payto Architects, Inc., Cleveland, Ohio
  • Construction Management: Welty Building Company, Akron, Ohio
  • Total Budget: $ 1,224,319 (local funds)