Schrank Hall Renovation

288,660 gsf of renovations including asbestos abatement of materials and roof replacements in Schrank Hall North & South including removal of the abandoned cooling tower (UAK99019 & UAK99020 combined with this project). Total replacement of the plumbing system in Schrank Hall South including mechanical room improvements, Electrical distribution improvements, ADA elevator modifications, Oil switch replacement (UAK99015 combined with this project) and Fire alarm replacement (UAK99013 combined with this project).Plaza and parking deck renovations.


Details

  • Construction Start Date: December 2002
  • Construction Complete Date: August 2002
  • Professional Design Services: Hasenstab Architects, Inc., Akron, Ohio
  • Interior Design Services: Ozanne Construction Company Inc., Cleveland, Ohio
  • Total Budget: $6,153,562